2009 edition of my "State of the IT Union" survey Jon Erickson's blog http://www.ambysoft.com/surveys/stateOfITUnion200907.html 125 participants Cost estimates: 21% no initial cost estimates if they do, then on average estimates are off by +/- 11% 39% do not track cost if they do, then on average they stay within +/- 19% "Techniques" * 72% indicated that their project teams will extend the schedule so as to deliver on the promised scope * 63% descope towards the end of the project to meet the deadline * 39% avoid "scope creep" whenever possible via a "change management" process * 34% will ask for extra funds * 32% have a flexible scope from the beginning of the project * 26% have a flexible schedule from the beginning of the project * 18% pad the budget * 18% change the original schedule to reflect the actual results * 13% have a flexible budget from the beginning of the project * 12% take a stage-gate approach to funding * 10% change the original estimate to reflect the actual results